Project

Refurbishment of Engineering Workshops, NESCOL, Fraserburgh
Full strip out, reconfiguration and refitting of the main Engineering Workshop


Completed to a very tight timescale during the College summer recess in 2014, this project comprised the full strip out, reconfiguration and refitting of the main Engineering Workshop.

The workshop layout was re-configured to provide an open plan facility, which was fully serviced with new high quality floor treatment installed, re-installation of existing equipment and the installation of new engineering equipment.

The building remained in use by staff throughout the works and all other facility operations remained functional.

location :

North East Scotland College, Fraserburgh


architect :

Arch Henderson


engineer :

AMS


surveyor :

WI Talbot & Partners


cdm-c :

Mitie Technical Facilities Management


duration :

8 weeks